A cutover date set too early becomes a constraint that degrades every other decision. Start with the criteria instead.

Telecom antennas on a rooftop at sunset
AI-generated illustration

Upgrading a BSS to a new major version, or migrating to a new platform, is among the riskiest operations an operator can undertake. Customers, offers, balances, billing history: everything must move with no visible interruption of service.

Start with criteria, not with a date

It is tempting to announce a cutover date at programme launch. It structures the plan and reassures leadership. But a date set before the go/no-go criteria are defined becomes a constraint that pushes teams to cut testing, accept gaps and defer fixes. We recommend the opposite: first define what must be true to cut over, then derive the date.

Rehearsals are the real plan

  • Successive dry-run migrations on real volumes, timed, with systematic reconciliation of migrated data.
  • A tested rollback plan, not just a written one: the decision to roll back must be possible to make and execute within the planned window.
  • A post-cutover service verification (VSR) prepared as a deliverable in its own right, with reference customer journeys.

Governing the cutover night

On the day, the question is no longer technical but about decisions: who decides to continue or stop, based on which indicators, at what time? These decision points, the go / no-go gates, are prepared weeks in advance and rehearsed like everything else.

A successful migration often looks like a non-event. That is exactly the goal.